Lithium fell, cells held, and most news was intent, not capacity
Five conclusions
“Most of the new orders and plans were still intent rather than operating capacity.”
Oct 23 to Nov 2, 2026. Events dated before Oct 23 are labelled as context where they appear.
Read it by status
Export VAT rebate at 6%, 2% consumption tax, Samsung SDI Indiana line in mass production, ACME 781.4 MWh commissioned.
NDRC spot rules (draft), Lingwu award (contract unsigned), SECI RfS (issued).
CATL solid-state pilot 2027, Peak Energy plant Q1 2027, TENER+ 9 MWh.
How figures are labelled
The cninfo, HKEX and KRX originals are not available; each figure is relayed by the outlet named in its row.
Broker and Intertek projections, vendor performance claims and draft rules are labelled where they appear.
Items dated before Oct 23, or data for earlier months such as July, are marked context and not counted as window events.
What moved at a glance
| Item | Value | Date | Source |
|---|---|---|---|
| SMM battery-grade lithium carbonate, spot average | RMB 100,050/t (97,700–102,400) | 28 Oct 2026 | SMM |
| SMM lithium carbonate spot, approximate | Around RMB 90,000/t; about 38% below Q3 average of RMB 147,500/t | 30 Oct 2026 | SMM |
| Benchmark LFP 314 Ah cell, EXW China | US$54.21/kWh; Q3 vs end-June −1.8% | Sep 2026 (publication date not stated) | Benchmark |
| Lingwu, Ningxia shared-storage award, 1 GW / 4 GWh | CNY 3.64 bn (US$535 m); implied RMB 0.91/Wh; contract unsigned | Award notice 26 Oct 2026 | ESS News |
| Samsung SDI Q3 revenue / ESS orders | KRW 4.69 tn (+52.6%) / 60 GWh (nine months) | 29 Oct 2026 | ESN |
| EVE Energy storage-cell shipments | 67.52 GWh, nine months (+39.46%) | 23 Oct 2026 | ESS News |
| Sungrow nine-month net profit | RMB 6.599 bn (−44.46%) | 30 Oct 2026 | Cailian via moomoo |
| SECI standalone BESS RfS (Rajasthan, Gujarat) | 4 GW / 16 GWh; RfS issued | 28 Oct 2026 | SolarQuarter |
| NDRC draft Basic Rules for Electricity Spot Markets | Comments to 18 Nov 2026; proposed start 1 Jan 2027 | Released 19 Oct 2026 (context) | CNESS; Sohu |
Lithium is down about 38%, yet cell quotes lag
Spot lithium and cell prices
SMM spot average, RMB/t, in the window (Oct 26, 27, 28), and the approximate level on Oct 30. Dashed lines are the Q3 average (SMM spot) and the cost-support estimate near RMB 80,000/t (UBS and Macquarie, estimate).
Benchmark LFP prismatic 314 Ah, EXW China, US$/kWh, with month-on-month change. Q3 2026 review, publication date not stated: context, not in-window quotes. No in-window InfoLink or SMM cell quote is available, so a weekly cell table is not built.
The Oct 28 rebound was technical
LC2701 (SMM’s most-traded contract) hit 101,520, fell to 92,320 and closed at 93,300, on volume up 17.6% to 398,200 lots and open interest up 9,791 to 448,900. SMM read this as bears in control, with upside “likely capped”.
Drivers per SMM: ore arrivals are rising and cathode schedules are weakening. Bald Hill and Finniss are returning and a Mt Marion expansion is approved. Argentina’s September carbonate exports were 10,600 t (+25.99% month on month, SMM flash, Nov 2).
Sep 2026 cell basis
CIF North America about 20% above EXW China and Europe about 16% (Benchmark; China-to-US freight).
Standard LFP prismatic cells in China fell 5.1% to 57.37; the global Li-ion price fell 4.0% to 71.85 (Benchmark).
Why cells move more slowly than lithium
Benchmark says July's cell spike reflected June's lithium. The 16 September carbonate drop came too late for the 30 September assessment, so it expects lagged cuts in Q4.
SMM's H1 gross margins: lithium mining up to 74%, salt processing 27–42%, cathode 5–14%, cells 12–23%. Q3 single-quarter profit fell 43% (Tianqi), 68% (Ganfeng) and 83% (Tianhua) quarter on quarter, while Salt Lake, with its own low-cost resources, fell about 12%.
Dynanonic's inventory was RMB 2.26 bn, up 82% since the start of the year; its operating cash flow was −RMB 2.14 bn for nine months despite a 213% profit rise. Buyers also waited for long-term contract arrivals. SMM adds that to hold revenue after a one-third price fall, volume must rise nearly 50%.
A 2% battery consumption tax has been in effect since 1 September 2026; Benchmark lists whether producers absorb it as a Q4 watch item. China's pause on new cell-capacity approvals (reported, in place since mid-May and public in September) is under review to conclude by year-end. Intertek CEA expects the export VAT rebate removal on 1 January 2027 (upcoming) to soften cost deflation.
Between SMM’s Q2 and Q3 averages carbonate fell 14.2%, while EXW 314 Ah fell 1.8%, about one-eighth as much. The bases differ (quarterly average vs quarter-end), so read this as an order of magnitude.
What it means for buyers
Spot is about 38% below its Q3 average, but the only cell evidence is a September low of US$54.21/kWh (EXW China). How much of the October fall reaches cells is not yet observable.
UBS and Macquarie both cite about RMB 80,000/t, a further 11% below 90,000. SMM sees buyers’ interest at 90,000–95,000 on Oct 27.
Tax treatment, delivery basis (the North America premium) and lithium-linked pricing determine what a quote means. This is description, not procurement advice.
New InfoLink and SMM weekly cell prints, the Q4 pass-through Benchmark expects, and SMM’s later daily reviews.
Lithium carbonate timeline, 2026 (RMB/t; window = Oct 23–Nov 2)
| Date | Value (RMB/t) | Type and publisher | Window? |
|---|---|---|---|
| 13 May | Spot high 200,500 (SMM); GFEX benchmark-contract high 210,580 (Market Index) | Spot; futures | Context |
| Q3 | Average 147,500 (Q2: 171,900; −14.2% QoQ) | SMM spot quarterly average | Context |
| 22 Oct | GFEX benchmark close 94,180 | Futures, Market Index | Context |
| 23 Oct | GFEX benchmark close 97,280 | Futures, Market Index | Window |
| 26 Oct | Avg 98,300 (96,400–100,200); LC2701 settlement 95,280 (+1.58%) | SMM spot; futures | Window |
| 27 Oct | Avg 99,350 (97,000–101,700); LC2701 close 98,500 | SMM spot; futures | Window |
| 28 Oct | Avg 100,050 (97,700–102,400); LC2701 close 93,300, settlement 96,460 | SMM spot; futures | Window |
| 30 Oct | “Around 90,000” | SMM spot, approximate | Window |
| 2 Nov | Spot “edged down by 100”; level not available | SMM headline | Window |
Broker views on lithium (estimates, via Market Index)
| Broker (date) | Demand growth 2026 / 2027 | View (estimate) |
|---|---|---|
| UBS, Sky Han (26 Oct) | 26% / 19% | BESS destocking is the key driver; supply growth ~18% to 25%; no rebound before year-end; cost support ~RMB 80,000/t |
| Canaccord (23 Oct) | 29% / 16% | 2026 demand raised 14% to 1.8 Mt LCE on BESS; mine supply +1.35 Mt LCE to 2030 |
Macquarie, also cited by Market Index, sees GFEX near the cost curve’s upper end (~105,000) and the next support near 80,000.
Benchmark LFP prismatic 314 Ah cell prices (US$/kWh)
| Month, 2026 | EXW China | CIF Europe | CIF North America |
|---|---|---|---|
| Jul | 57.75 (+4.6%) | 67.11 (+4.3%) | 64.99 (+4.4%) |
| Aug | 53.15 (−8.0%) | −7.4% | −7.6% |
| Sep | 54.21 (+2.0%) | 62.97 (+1.3%) | 64.78 (+7.4%) |
| Q3 vs end-June | −1.8% | −2.2% | −4.1% |
All figures from Benchmark, Q3 2026 review (context).
Q3 results split the field: volume up, margins mixed
Year-on-year change, as reported
Metrics differ by company and period (revenue, shipments or net profit; Q3 or nine months). All company-reported, relayed by the outlets named in the table below; read each bar by its label.
“EVE and BYD grew profit on higher volume, while Sungrow’s nine-month profit fell 44.46% and its Q3 gross margin dropped 9.17 points in one quarter.”
Volume vs cash
Nine-month net profit RMB 5.24 bn (+86.11%), but operating cash flow fell 65.37% to RMB 1.698 bn.
Q3 net profit RMB 10.02 bn was 12% to 23% below Reuters-polled broker expectations.
Company detail
Announced 2026-10-29 (company-reported, relayed by ESN). The Battery Business earned KRW 361.9 bn on KRW 4.41 tn (+55.3%), which the company ties to ESS and battery-backup sales linked partly to AI data centres. It expects the ESS market to “maintain momentum” in Q4. The quoted growth rates do not match the rounded figures (4.69 / 3.05 = +53.8%, not +52.6%); the stated rates are used. No Q3 figures dated in the window from LG Energy Solution or SK On.
Reported on the evening of 2026-10-23. Nine-month net profit was RMB 5.24 bn (+86.11%), but operating cash flow fell 65.37% to RMB 1.698 bn. Management said Q4 capacity is fully booked and Q1 2027 schedules are not finalised (company says). No Q3 storage margin is disclosed; the latest is H1 (context): RMB 15.09 bn revenue at 12.51% gross margin.
Reported on 2026-10-30. Sungrow's Q3 net profit, storage GWh and Q4 storage-shipment guidance are not available. EnergyTrend lists Sungrow, BYD, Deye, HyperStrong and Gotion as reported, but only Sungrow's profit is visible; for Deye only its 2026-10-14 forecast (context): nine-month net profit RMB 4.22–4.32 bn, +79.81% to +84.07%.
Filed with HKEX on 2026-10-29 (Electrek; BitAuto says 10-30). Nine-month revenue was flat at RMB 566.30 bn and net profit fell 4.2% to RMB 22.34 bn; Q3 exports were 550,704 vehicles (+137%) and inventory is up 60% since January. Electrek's calculated Q3 gross margin is about 18.0% (media-derived). No BYD storage-segment figure is available.
Great Power (10-26) has a net margin of 5.3% against about 7.4% in H1 and links higher inventory write-downs to the lithium-carbonate fall and consumption tax. The SNE ranking is relayed on CATL's newsroom on 2026-10-26 (a fifth straight year at the top); no volumes or lower ranks are given. ESS News places EVE among the three largest storage-cell suppliers with CATL and Hithium. Context from the previous issue: CATL's Q3 gross margin fell from 23.15% to 20.69% (10-20); Tesla's energy revenue fell 16% on 13.7 GWh (10-21).
Results at a glance
| Company | Metric (period) | Value | YoY | Date | Source (company-reported) |
|---|---|---|---|---|---|
| Samsung SDI | Revenue (Q3) | KRW 4.69 tn (≈US$3.5 bn) | +52.6% | 2026-10-29 | ESN |
| Samsung SDI | Operating profit (Q3) | KRW 407.8 bn | n/a | 2026-10-29 | ESN |
| Samsung SDI | ESS orders (9M) | 60 GWh | n/a | 2026-10-29 | ESN |
| EVE Energy | Group revenue (Q3) | RMB 27.70 bn | +64.56% | 2026-10-23 | BigGo |
| EVE Energy | Storage-cell shipments (9M) | 67.52 GWh | +39.46% | 2026-10-23 | ESS News |
| Sungrow | Net profit attributable (9M) | RMB 6.599 bn | −44.46% | 2026-10-30 | Cailian via moomoo |
| BYD | Revenue (Q3) | RMB 221.49 bn | +13.59% | 2026-10-29/30 | TipRanks |
| BYD | Net profit attributable (Q3) | RMB 10.02 bn | +28.08% | 2026-10-29/30 | TipRanks |
The cninfo, HKEX and KRX originals are not available, so every figure is company-reported but relayed by the outlet named in each row.
Orders were mostly intent, and US rules sort the market
Order book in the window, GWh
EVE and Fluence (up to 206 GWh) is a September framework agreement, so it is context and not drawn. The LGES bar is the roughly 2 GWh over 24 months; talks on 4.5 GWh are not counted.
Capacity is full at the top
Samsung SDI says more than 60 GWh of orders keep its SPE and Ulsan lines full through 2028; EVE says Q4 capacity is fully booked (Oct 23); CATL says, citing PV Tech Research, that utilisation stayed above 90% in H1 2026.
| Company | Customer | GWh | Type | Date |
|---|---|---|---|---|
| Samsung SDI | Alpha Omega Power (US IPP) | 1.0 new; 1.5 cumulative | Signed contract value not disclosed | 2026-10-26 |
| LG Energy Solution | Energix (Israel-HQ developer) | ~2 (1.5 Europe + 0.5 US) over 24 months; talks on 4.5 | Non-binding MoU | 2026-10-27 |
| CATL | Intilion (Germany, Switzerland, Austria) | 3 over 5 years | MoU | 2026-10-27 |
| EVE Energy | Fluence | up to 206 (16 firm 2027 + 190 reserved 2028–31) | Framework agreement · context | Sept 2026 |
Cells for Alpha Omega come from the StarPlus Energy plant in Kokomo, Indiana, for delivery by end-2026. The Intilion headline mentions sodium-ion, but the body names only CATL’s TENER systems, so the chemistry of the 3 GWh is not stated. No window item on Hithium’s long-duration cell orders.
| Company | Site | Capacity | Stage (vs 2026-11-03) | Date |
|---|---|---|---|---|
| Deye Energy Storage | Cixi Binhai | 16 GWh C&I line (7 + 9 GWh phases) | Phase II land won for RMB 103.587m; agreement signed 2026-06-23; not built | Announced 2026-10-22 (context) |
| Samsung SDI | SPE, Kokomo, Indiana | ESS LFP line; two more from H1 2027 | Mass production since early Oct 2026 | 2026-10-29 |
| Samsung SDI | SynergyCells, New Carlisle (27 GWh) | ESS LFP | Wholly owned since Aug 2026; mass production plan H2 2028–early 2029 | 2026-10-29 |
| Gotion | Lujiang | 200,000 t/yr cathode material | Full production | 2026-10-29 |
| Sigenergy–Failte | India, site not chosen | Inverter plant, then ESS plant; size not stated | Reported approvals in progress | 2026-10-23 |
Deye’s “100M yuan” headline is the land price; total project investment is not stated. Sigenergy’s plan comes from an expo interview, not a company announcement. LG Energy Solution’s only capacity figure is Intertek CEA’s 33 GWh across three factories.
| Rule | Threshold | Status on 2026-11-03 |
|---|---|---|
| Prohibited foreign entity (PFE) test; “FEOC” is the older term | One specified entity ≥25%; combined ≥40%; debt ≥15%; licence signed or amended on or after 2025-07-04 | In effect |
| Material assistance cost ratio, §48E storage | 55% (construction begins 2026); 60% (2027) | 55% in effect 60% upcoming |
| Treasury “effective control” guidance | Due 2026-12-31 | Upcoming none published when checked |
About 11% of announced 2026 US production capacity may slip into 2027. Korean cathode makers L&F, Posco and EcoPro announced about 23 GWh of LFP cathode capacity for 2026, enough for nearly 40% of US demand if fully realised (estimate). Intertek expects tax-credit eligibility to split the market into price tiers.
The test turns on who owns or controls the maker, not where the cell is made. Cells are 52.0% of grid-scale direct cost in the IRS interim table, so cells from a PFE leave a ratio of 48%, below 55%. China Prospect is secondary and undated.
Solid-state and sodium-ion stayed at sample or plan stage
“In this window no solid-state cell went beyond the sample stage or a 2027 pilot plan, and sodium-ion advanced mainly as demonstration slices and a US plant not yet built. The concrete gains were in format: a 9 MWh container and a 790 Ah cell.”
Readiness table
| Technology | Company | Milestone | Stage (as of 2026-11-03) | Date |
|---|---|---|---|---|
| All-solid-state (sulfide) | CATL | 20 Ah samples; small-batch pilot 2027 | Sample pilot planned | 2026-10-27 |
| All-solid-state | Samsung SDI | Samples Sept 2026; humanoid target H2 2027 | Sample customer evaluation | 2026-10-29 |
| Solid-state (polymer) | Sunwoda | Customer sample testing | Sample | 2026-10-30 |
| Sulphide electrolyte | Solid Power | MOBIUS 45 mt/yr line | Commissioning operation Q4 2026 | 2026-10-26 |
| Lithium sulfide | Tianqi Lithium | 50 mt/yr pilot line | Under construction end-2026 plan | 2026-10-28 |
| Solid-state Li-metal | QuantumScape | 100 MWh line, cells from 2028 | Plan pilot line operating | 2026-10-21 · context |
| Sodium-ion BESS | Peak Energy | 4 GWh Sacramento plant | Plan production Q1 2027 | 2026-10-21 (context); reported 10-23 |
| Sodium-ion BESS | CATL TENER Sodium | >30 MWh per system | Vendor claim mass-produced | 2026-10-28 |
| Large-format LFP | Envision AESC | 790 Ah cell, Renqiu tender win | Awarded commissioning end-2026 | 2026-10-29 |
| 9 MWh container | CATL TENER+ | Global launch | Launched (vendor claim) | 2026-10-28 |
| Vanadium flow | Delectrik | 20 MW/120 MWh, 6 h | Awarded | 2026-10-27 |
Solid-state
Pilot production starts in 2027; moved from a 10 Ah-class platform to 20 Ah samples; no customer, output or vehicle date. The roughly 500 Wh/kg target is not confirmed as a production specification.
Samples to humanoid customers in September 2026; commercialisation targeted for H2 2027. SMM, citing foreign media, reports a 900 Wh/L target vs roughly 650 Wh/L for liquid-electrolyte cells.
Design and process verification complete, customer sample tests under way; only a 0.2 GWh sample line is confirmed.
Sodium-ion
US$108 m Series B (Oct 21, context; reported Oct 23). The 4 GWh Sacramento plant (capex about US$71 m) starts production in Q1 2027; today’s cells come from Chinese makers.
Over US$1 bn of orders, not itemised: Jupiter Power up to 4.75 GWh over 2027–2030, Energy Vault 1.5 GWh and an RWE pilot. The only operating system is 3.5 MWh at SolarTAC; the up-to-20% lower cost of energy is unverified.
Shown in Australia for the first time; exceeds 30 MWh per system, more than 10,000 cycles at 45 °C, 95% round-trip efficiency, over 20 years’ life: vendor claims.
Format and long-duration
About 9 MWh per liquid-cooled container, 25-year design life; CATL says 40% fewer containers and a 35% smaller footprint (vendor claims).
790 Ah prismatic cell, over 2.5 kWh per cell. Renqiu 100 MW/400 MWh is a 90% LFP / 10% sodium hybrid due by end-2026.
Delectrik awarded a 20 MW/120 MWh six-hour project by GIPCL in Gujarat.
Our judgement
Every solid-state item here is a sample, pilot line or dated target; none is capacity a storage buyer can order. Solid Power’s MOBIUS line (45 mt/yr, Oct 26) takes SP2 capacity to about 75 mt/yr; Tianqi’s 50 mt/yr lithium sulfide pilot (Oct 28) has samples at over 30 clients. Format scale-up is the near-term cost lever; sodium-ion and solid-state remain dated claims, not procurement options.
China’s one GWh-scale award is unsigned, and the policy is a draft
Price points, RMB/Wh
The bases differ: TD Research figures are July system averages, Ningdong is a signed equipment-and-installation contract (date not stated, “earlier in October”), and Lingwu is an implied price for equipment plus construction. Ratios are indicative only.
CNY 3.64 bn (US$535 m) ÷ 4,000 MWh. No contract signed; the split among the three consortium members is not disclosed. Wuhan Tianyuan warns payment terms are open and the project may change or be delayed.
Against July
0.91 ÷ 0.58 = 1.57×, or +57%. Ningdong is 0.65 ÷ 0.58 = 1.12×, or +12%. Months and scopes differ.
Lingwu covers design, civil works, a new 330 kV substation, about 4 km of transmission, commissioning and grid connection, plus a two-year warranty.
Awards and tenders
| Project | Owner / winner | MW / MWh | Value | Date and status |
|---|---|---|---|---|
| Lingwu, Ningxia, shared storage | Owner Lingwu Huaxin Comprehensive Energy Service; Wuhan Tianyuan-led consortium | 1,000 / 4,000 | CNY 3.64 bn (US$535 m) | Award notice confirmed 2026-10-26; contract not signed |
| Renqiu, Hebei, standalone | Envision Energy Storage (LFP system) | 100 / 400 | Not stated | Win announced 2026-10-29; completion planned end-2026 |
| Yumen, Gansu, standalone shared | Narada Power (builder, cell supplier) | 200 / 800 (phase I 100 / 400) | Not stated | Phase I grid-connected, announced 2026-10-30 |
Lingwu: a consortium of Wuhan Tianyuan (lead), Inner Mongolia Yinhe Electric Power Installation Engineering and Ningxia Communications Construction. Grid-connection notice is due by 2027-04-30 and acceptance by 2027-10-30. Renqiu is billed as one of China’s first standalone demonstrations mixing LFP (90%) and sodium-ion (10%), with 790 Ah cells. Hoenergy’s agreement with Octopus Energy (Oct 30) states no volume or value, so it is not an order.
Policy changes and status
| Policy | What it does | Status at 2026-11-03 |
|---|---|---|
| NDRC draft Basic Rules for Electricity Spot Markets | Supports joint bidding by renewables and co-located storage (Art. 8); names new-type storage as a market entity; nodal pricing; daily clearing, monthly billing | Draft released 2026-10-19 (context); comments to 2026-11-18 (upcoming); proposed start 2027-01-01, valid five years |
| NDRC Document 136 (2025) | Storage no longer a precondition for new-energy approval or grid connection | In effect |
| NDRC Document 114 (2026) | First national recognition of capacity value for new-type storage | In effect issue date not stated |
| MOF/STA Announcement No. 2 (2026) | Battery export VAT rebate 9% to 6% from 2026-04-01; cancelled from 2027-01-01 | 6% in effect cancellation upcoming |
| 2% consumption tax, lithium-ion batteries | Domestic levy | In effect since 2026-09-01 |
NDRC’s own announcement is not available; the draft is known from trade and financial press. Joint bidding is something NDRC “supports”, not a requirement; its economics depend on provincial rules. Nodal pricing as the default (Art. 23) and price-difference settlement (Art. 48) would widen the price spread storage earns, and the draft adds ramping as an ancillary service (Art. 42). The 2023 rules’ stated validity ended 2026-10-15, yet the successor would start only on 2027-01-01.
No TrendForce or CNESA monthly tender or award figure for September or October 2026 is available, so none is shown. Our judgement: capacity pricing (Document 114) is in force, but the spot-market layer is not; until provinces write detailed rules, rule text is a better guide to project returns than tender volume.
Overseas pipeline is large, but only 2.9% is commissioned
Tracker by stage, MWh
The tracker totals 26,620 MWh (ACME at its planned 1,200 MWh), of which only 781.4 MWh is commissioned. Every other row is tendered, permit-pending, financed, contracted or sold.
India: tenders outrun the fleet
5.3 GWh operating against 185 GWh under development; 5.3 ÷ 185 = 2.9%. SolarQuarter’s Oct 23 page cites about 9.3 GWh installed with no definition; we follow the CEA official.
Elsewhere
3.1 GW / 13.5 GWh operating, with another 3.7 GW in testing while already dispatching.
Nine projects (2.3 GW / 7.1 GWh) came online in H1 2026; 13 more (1.6 GW / 6.5 GWh) reached financial close.
Project tracker
| Project | Country | MW / MWh | Developer / supplier | Stage | Date |
|---|---|---|---|---|---|
| SECI standalone BESS, Rajasthan + Gujarat | India | 4,000 / 16,000 | SECI (buyer); bidders open | RfS issued | 2026-10-28 |
| Pulverdingen | Germany | ~1,000 / 4,000 | ADS-TEC Energy | Permit pending | 2026-10-28 |
| TNPDCL solar + storage, Tranche XXI | India | 300 / 1,800 | TNPDCL via SECI | Regulator approved | order 2026-10-22 |
| Ełk + Turośń Kościelna | Poland | 400 / 1,600 | Greenvolt to A&R Investments | Built; sale agreed, not closed | 2026-10-23 |
| ACME FDRE, Bikaner | India | 300 / 1,200 | ACME Solar | 781.4 MWh commissioned | 2026-10-29 |
| Samsung SDI supply to Alpha Omega Power | US | n/a / 1,000 | Samsung SDI America | Signed contract | 2026-10-26 |
| Baixas + Coquainvilliers | France | 200 / 800 | Recurrent Energy to BW ESS | Sold; still in development | 2026-10-29 |
| GIPCL Vadodara flow battery | India | 20 / 120 | Bondada (EPC); Delectrik (flow-battery start-up) | EPC awarded; award confirmed | 2026-10-23 / 27 |
| Dandara phase 1 | Egypt | n/a / 100 (+569 MW solar) | Scatec | Financing agreed | 2026-10-29 |
By region
Terms are from SolarQuarter (the RfS itself is not available). VGF arithmetic: INR 15 lakh × 16,000 MWh = INR 2,400 crore, about US$253 m at roughly INR 95/US$ (derived). CEA's Prashant Bhamu said VGF of INR 90 bn supported 13.2 GWh and a separate 30 GWh scheme brings supported capacity to 43.2 GWh; storage obligations for distribution utilities rose from 1% to 4%, and safety standards start in April 2027 (upcoming). SECI says bidders per tender grew from six or seven to more than 20, but construction takes 15–18 months. ACME Solar's Bikaner FDRE reached 195.35 MW / 781.40 MWh, 65.1% of its planned 300 MW / 1,200 MWh. TNERC's 22 Oct order (reported 26 Oct) approved TNPDCL's 300 MW / 1,800 MWh system at INR 3.12/kWh plus a INR 0.07 SECI margin, on a 25-year PPA.
Asset rotation, not new orders. ADS-TEC said on 28 Oct that the authority confirmed its application complete and expects the permit shortly; construction has not started and ADS-TEC intends to sell a majority stake. The Polish projects were completed in Q3 2026 and hold 17-year capacity-market contracts from 2028, paying for 85% of rated capacity, plus 10-year tolling. Nothing dated in the window on Portugal's grid-access tender, Italy's MACSE derating, Bulgaria or Germany's nine-month installations.
13 projects (1.6 GW / 6.5 GWh) reached financial close; pv magazine does not name the source of the grid-scale figures. The SRES cap rose from 100 kW to 1 MW on 1 October (in effect), cutting qualifying upfront cost by about 20%. Sigenergy launched a 401 kWh C&I cabinet; its claim of 54.5 m² per 4 MWh is a vendor claim. CATL's 9 MWh TENER+ debut is covered under technology. No CIS tender 8 result or dated home-battery rebate step-down.
The Samsung Battery Box 1.7 uses NCA cells made at StarPlus Energy in Kokomo, Indiana, due for delivery by end-2026, with AOP construction in WECC and ERCOT starting in 2027; its 17% higher energy density than SBB 1.5 is a company claim. ACERA's projection is that operating capacity could triple within twelve months. Dandara phase 1 pairs 569 MW of solar with a 100 MWh battery for Egypt Aluminium under a 25-year sovereign-guaranteed PPA, with COD targeted for H1 2028; status is financing agreed, per SolarQuarter. Nothing in the window on Saudi Arabia, Egypt's Nag Hammadi or Eskom.
Contract terms and rule text will decide the next 60 days
“The next 60 days will be settled by contract terms and rule text, not by chemistry: how far lithium’s fall reaches cell quotes, whether NDRC’s draft spot-market rules survive their comment period to 2026-11-18, and what changes when the export VAT rebate ends on 2027-01-01.”
Storage buyers
Lithium spot fell to about RMB 90,000/t by 30 Oct; the only cell series fell 1.8% in Q3.
Spot and cell quotes run on different clocks; Benchmark expects lagged cuts in Q4, so tax treatment, delivery basis and lithium-linked terms decide what a quote means.
China developers and EPC firms
One GWh-scale award (Lingwu, implied RMB 0.91/Wh, contract unsigned); NDRC spot rules still a draft.
Award prices include construction scope; revenue depends on provincial rules still to be written.
Cell and system makers
Samsung SDI cites 60 GWh of orders and EVE says Q4 capacity is fully booked, while Sungrow's Q3 gross margin fell to 29.45% from 38.62%.
Tier-1 cell suppliers have pricing room; margin pressure shows at integrator level.
Overseas developers
SECI issued a 4 GW / 16 GWh RfS; India has 5.3 GWh operating against 185 GWh under development.
Stage matters: in the tracker only 781.4 MWh of 26,620 MWh (2.9%) is commissioned.
US-exposed suppliers
Prohibited-foreign-entity test in effect; 55% cost ratio in effect, 60% upcoming; about 11% of 2026 US capacity may slip to 2027 (Intertek).
Credit eligibility may split the market into price tiers.
Technology scouts
Solid-state at sample or 2027 pilot stage; sodium-ion plant not yet producing.
None is orderable now; format scale-up (9 MWh, 790 Ah) is the near-term lever.
Readers of company results
Nine-month totals still carry the first-half price rise, while Q3-only profit fell 43% (Tianqi), 68% (Ganfeng) and 83% (Tianhua) (SMM).
Single-quarter figures show the turn earlier than cumulative ones.
Prices and orders
The lithium move has not finished passing through. UBS expects no rebound before year-end; UBS and Macquarie point to support near RMB 80,000/t (estimates). Against that, Intertek expects the end of the export VAT rebate on 2027-01-01 to soften cost deflation.
One signed contract (1 GWh) sat beside two MoUs (about 5 GWh), and Samsung SDI says its SPE and Ulsan lines are full through 2028. Delivery, not demand, is the constraint to watch.
Buyer checklist
Tick items as you work through them. Description, not investment, procurement or legal advice.
RelyEZ (9621) global offering closes; pricing expected 11-05, dealing 11-09.
NDRC draft spot-market rules, comment deadline; proposed start 2027-01-01.
Export VAT rebate at 6% ends; it is cancelled from 2027-01-01. Treasury effective-control guidance is also due.
Key dates
Status is judged against the run date, Nov 3, 2026.